EPS provides distribution engineering and construction for utility, industrial, and governmental clients. Our project experience includes:

East End Road Utility Relocation

The Department of Transportation (DOT) elected to upgrade East End Road in Homer, Alaska. Before the new road could be constructed, the impacted utilities along the old road would require relocation. Homer Electric Association (HEA) contracted with D&L to design a final relocation. D&L prepared the final relocation plan, prepared construction technical specifications and provided construction support. The corridor along East End Road contains many different utility facilities, including power, communication, water, sewer, and gas. Upgrading the road created conflicts with these existing facilities. HEA began the preliminary design of the new distribution system and tasked D&L with completing the design and preparing necessary construction plan drawings and bid documents. This project replaced the existing overhead distribution system with an underground double circuit feeder (express and distribution) and a relocated overhead system as terrain and other facilities allowed. It required working in cooperation with DOT, the road designer, as well as telephone, cable, and natural gas utilities. The final design of the underground system incorporated a joint trench shared by multiple utilities.

East End Road Utility Relocation - Homer, Alaska

Cordova Airport Feeder

Project consisted of design and construction management of a new underground distribution feeder to the Cordova Airport. This is a unique underground project adjacent to an existing roadway and wetlands. Crossing of multiple drainages and standing water required horizontal borings in selected areas. Trenching sections were required to match-up with the borings. Underground vaults located in the roadway fills were installed flush with the slope to allow for standard road maintenance. An existing underground cable needed to remain in service during construction for supply to the airport and navigational lighting. Close coordination with DOT/PF and the airport was essential.

EPS Distribution

O’Malley Road Underground Installation Of 12.5 kV Distribution & 34.5 kV Sub-Transmission Lines

This project consisted of the design for an overhead to underground relocation of 12.5 kV distribution and 34.5 kV sub-transmission lines. Designs for overhead and underground secondary services, sections of overhead 12.5 kV and overhead double and triple circuit 12.5/34.5 kV were also part of this project. Road crossings required extensive use of horizontal borings for the length of the project. The underground installation was in preparation for a 138 kV transmission line we were also designing. Plans for road re-grading and widening along the O’Malley Road Corridor necessitated substantial coordination with DOT.

Walden Point Line Extension

This project involved the preparation of a complete design package including field staking and construction documents for a 35 kV line extension from the Metlakatla Power House to the Walden Point Ferry Terminal, from the Walden Point Ferry Terminal, across Revillagigedo Channel via submarine cable to Mountain Point Substation on the Ketchikan Public Utility system. Pole assemblies were based on RUS specifications for 35 kV construction and RUS recommendations for raptor protection.

Terra Southwest Williamsport To Pile Bay Communications Line

For this project Dryden & LaRue designed a fiber optic communications line from Williamsport in Cook Inlet to Pile Bay on Lake Iliamna. The terrain traversed by this line is largely mountainous. Typical aerial and buried plant standards (primarily from United States Department of Agriculture, Rural Utility Systems (RUS) and GCI) were used in compiling the construction units for this project. The plant standards were utilized in conjunction with Design Criteria developed by Dryden & LaRue in response to the expected environmental conditions in this region of Alaska.